Information and communication
May 2023 – February 2024 – notices, meetings with AA boards Preparation of the reconstruction decision
June 2023 – June 2024 – Building inspections, mapping of reconstruction requirements
June 2023 – August 2024 – Preparation of energy labels (weighted energy consumption WEC) and entry in Estonian Building Register (Ehitisregister, EHR)
June 2023 – August 2024 – Preparation of reconstruction plans, profitability analyses, requesting loan conditions from banks.
June 2023 – August 2024 – conducting general meetings of AAs  
Preparation for reconstruction
July 2023 – August 2024 – Technical consultant and design service quality trainings for AA boards
July 2023 – October 2024 PV panel (solar panel) simulations
June 2024 – April 2025 – Evaluation of construction projects, elaboration of profitability analyses
June 2024 – May 2025 – conducting the general meetings of AAs to decide on applying for reconstruction loan  
Reconstruction
August 2024 – August 2025 – Elaboration of profitability analyses based on the results of construction procurements
September 2024 – September 2025 – holding general meetings of AAs to decide on reconstruction
September 2024 – September 2025 – Conclusion of construction contracts by AAs
July 2024 – September 2025 – Preparation of the construction quality monitoring guide for AAs and Technical consultants and organization of trainings