Information and communication

  • May 2023 – February 2024 – notices, meetings with AA boards

Preparation of the reconstruction decision

  • June 2023 – June 2024 – Building inspections, mapping of reconstruction requirements
  • June 2023 – August 2024 – Preparation of energy labels (weighted energy consumption WEC) and entry in Estonian Building Register (Ehitisregister, EHR)
  • June 2023 – August 2024 – Preparation of reconstruction plans, profitability analyses, requesting loan conditions from banks.
  • June 2023 – August 2024 – conducting general meetings of AA-s

Preparation for reconstruction

  • July 2023 – August 2024 – Technical consultant and design service quality trainings for AA boards
  • July 2023 – October 2024 PV panel (solar panel) simulations
  • June 2024 – April 2025 – Evaluation of construction projects, elaboration of profitability analyses
  • June 2024 – May 2025 – conducting the general meetings of AA-s to decide on applying for reconstruction loan.

Reconstruction

  • August 2024 – August 2025 – Elaboration of profitability analyses based on the results of construction procurements.
  • September 2024 – September 2025 – holding general meetings of AAs to decide on reconstruction.
  • September 2024 – September 2025 – Conclusion of construction contracts by AAs
  • July 2024 – September 2025 – Preparation of the construction quality monitoring guide for AAs and Technical consultants and organization of trainings